Now - October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
10/13/2011 – SAP release of year end base level support pack
10/17/2011 - End of day production snapshot to be used to refresh test environments
10/24/2011 - Development Freeze begins
11/01/2011 - Last date to implement support & enhancement changes until freeze ends on 12/7/2011
10/28/2011 - 11/4/2011 Unit test
11/7/2011 - 11/28/2011 System Integration Test
12/2/2011 - 12/4/2011 Go-live weekend!
12/7/2011 - Development Freeze endsERP 6.0 w/EHP4 HR SP27 to ERP 6.0 w/EHP5 HR SP17(the Support Packs)
NetWeaver 7.00 with EHP1 (7.01) to NetWeaver 7.00 with EHP2 (7.02)
SAP Application Server kernel (to most current version to be released in October)
Oracle db 11.2.0.1 to 11.2.0.2 (the most current patch)
BSI TUBs
Other updates
ØGUI Upgrade to 7.20 (now through SP Application)
ØData Sync Manager 3.14.2 to Data Sync Manager 3.18
Authorization Enhancement