Comment: Dynamic Task List: Task added to list 'Pre-Update Schedule and Processes'

...

Cutover plan - Work in progress - tasks and dates NOT finalized.

...

Tasklist
title
width80%
Pre-Update Schedule and Processes
Pre-Update Schedule and Processes
width80%

||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1319222115555|          |donovan@mit.edu|*Tuesday, 11/22/2011, by 9AM*  Post messages on SAPweb and ESS Web sites of upcoming SAP outage.|
Tasklist
width80%
titleSupport Pack Application and Processes

...