Comment: Dynamic Task List: Marked all tasks incomplete in list 'Post Upgrade Schedule and Processes'

...

Tasklist
Post Upgrade Schedule and Processes
Post Upgrade Schedule and Processes
width80%
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|TF|M|F|1319224799246|1321631276370          |donovan@mit.edu|*Sunday, 12/4/2011, 8 AM*  Validation reports executed (trial balance reports).|
|TF|M|F|1319224847250|1321631295555          |donovan@mit.edu|*Sunday, 12/4/2011, 10 AM*  Unlock web-services ids in Production.|
|TF|M|F|1321631357748|1321631373902          |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM*  Enable Gateways (SAPWeb/ESS)|
|TF|M|F|1321631478081|1321631531105          |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* EDI Step 1: Update SAP EDI Version number|
|TF|M|F|1319224915007|1321631532028|donovan@mit          |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM*  EDI Step 2: Turn on the EDI 'gourmet-1' server|
|TF|M|F|1319224958553|1321631577397          |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM*  EDI Step 3: Schedule EDI job.|
|TF|M|F|1319225905482|1321631601600          |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM*  Email to ist-sap@mit.edu.|
|TF|M|F|1319226000923|1321631620346          |donovan@mit.edu|*Sunday, 12/4/2011, 11 AM*  R3-Admin Action Log.|
|TF|M|F|1319226039994|1321631630463|donovan@mit.edu|*Sunday,           |donovan@mit.edu|*Sunday, 12/4/2011, 12 PM - 2 PM*  ADMIN SYS Action log tasks.|
|TF|M|F|1319226077530|1321631639711          |donovan@mit.edu|*Sunday, 12/4/2011, By 2 PM*  Update voice message whether Data Validation is on schedule.|
|TF|M|F|1319226107914|1321631648288          |donovan@mit.edu|*Sunday, 12/4/2011, By 2 PM*  Unlock testers.|
|TF|M|F|1319226164776|1321631652068          |donovan@mit.edu|*Sunday, 12/4/2011, 2-4 PM*  PS1 Data Validations & Transaction processing.|
|TF|M|F|1319226219506|1321631715813          |donovan@mit.edu|*Sunday, 12/4/2011, By 4 PM*  Coordinators for each area should send email to sap-validation-team@mit.edu at the completion of the validation notifying results.|
|TF|M|F|1319226270713|1321631789603          |donovan@mit.edu|*Sunday, 12/4/2011, 4 PM*  _Conference Call Check-in Go/No-Go decision-use webex line_.|
|TF|M|F|1319226312531|1321631927207          |donovan@mit.edu|*Sunday, 12/4/2011, after conference call*  send email notifying results.|
|TF|M|F|1319226379715|1321631934654          |donovan@mit.edu|*Sunday, 12/4/2011, 8 PM - 12 AM*  Data Warehouse Job Validation.|
|TF|M|F|1319226413580|1321631937128          |donovan@mit.edu|*Sunday, 12/4/2011, 8-10 PM*  Unlock users.|
|TF|M|F|1319226433006|1321631940281          |donovan@mit.edu|*Sunday, 12/4/2011, 10 PM*  Enable Dropbox.|
|TF|M|F|1319226463541|1321631943265|1319226463541|          |donovan@mit.edu|*Sunday, 12/4/2011, 10 PM*  Eecute ProCard from Bank of America feed.|
|TF|M|F|1319226494960|1321631950026          |donovan@mit.edu|*Monday, 12/5/2011, 1:30 AM*  On line back up of PS1.|
|TF|M|F|1319226926024|1321631952304          |donovan@mit.edu|*Monday, 12/5/2011, By 6AM*  Update 3-down web page & SAPgui message.|
|TF|M|F|1319226958132|1321631960061          |donovan@mit.edu|*Monday, 12/5/2011, By 6 AM*  Remove SAPweb, ESS And EHS messages.|
|TF|M|F|1319227009224|1321631964621          |donovan@mit.edu|*Monday, 12/5/2011, 6 AM*  Email notification to MIT community stating update complete and production available.|
|F|M|F|1319227037379|          |donovan@mit.edu|*Monday, 12/5/2011, 9 AM*  Reinstate weekend MITSIS Grad Appointment feed.|