| Tasklist | ||||||
|---|---|---|---|---|---|---|
| ||||||
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1319222115555| |donovan@mit.edu|*Wednesday, 11/23/2011, by 9 AM* Post messages on insideMIT, SAPweb and ESS Web sites of upcoming SAP outage.|
|F|M|F|1319222167545| |donovan@mit.edu|*Wednesday 11/23/2011, 12 PM* Send message to MIT-SAP community about upcoming SAP outage.|
|F|M|F|1319222216395| |donovan@mit.edu|*Wednesday, 11/23/2011, 12 PM* Post message on SAPgui indicating upcoming SAP outage.|
|F|M|F|1319222262777| |donovan@mit.edu|*Wednesday, 11/23/2011, 11 AM* IS&T - Cutover weekend planning meeting.|
|F|M|F|1321629489192| |donovan@mit.edu|*By Sunday, 11/27/2011 8 AM* Download Basis notes for the PS1 required for the upgrade|
|F|M|F|1321629574243| |donovan@mit.edu|*Sunday, 11/27/2011, 8 AM* DSM Upgrade & associated notes.|
|F|M|F|1321629654586| |donovan@mit.edu|*Sunday, 11/27/2011 10 AM* Begin online upgrade piece of the application of Enhancement Pack(s)|
|F|M|F|1319222316994| |donovan@mit.edu|*Wednesday, 11/30/2011. 12 PM* Steering Committee Meeting - review cutover plan.|
|F|M|F|1319222474613| |donovan@mit.edu|*Wednesday, 11/30/2011, 10 AM-12 PM* SAP upgrade Core/Action log team meeting - review Cutover schedule and details.|
|F|M|F|1319222530271| |donovan@mit.edu|*Wednesday, 11/30/2011, 1 PM* Steering Committee, review test result, Go/No-Go decision.|
|F|M|F|1319222748441| |donovan@mit.edu|*Thursday, 12/1/2011, 9 AM* Email Steering Committee Go/No-go decision.|
|F|M|F|1319222941825| |donovan@mit.edu|*Thursday, 12/1/2011, 2-3 PM* Final review - RT issues, transport list, web components.|
|F|M|F|1319223014696| |donovan@mit.edu|*Thursday, 12/1/2011, By 4 PM* Schedule Pre & Post Trail balance reports.|
|F|M|F|1319223055588| |donovan@mit.edu|*Thursday, 12/1/2011, By 4 PM* R3-Admin email nessage about system down time.|
|F|M|F|1319223115685| |donovan@mit.edu|*Thursday, 12/1/2011, By 4 PM* Final copy of Production Update Schedule published and emailed.|
|F|M|F|1319223207714| |donovan@mit.edu|*Friday, 12/2/2011, By 12 PM (Noon)* Facility Supervisors print out work lists as back up for Monday morning.|
|F|M|F|1319223270013| |donovan@mit.edu|*Friday, 12/2/2011, By 12 PM (Noon)* Reschedule (shift) DW batch jobs to Sunday night.|
|F|M|F|1319223309453| |donovan@mit.edu|*Friday, 12/2/2011, By 4:30 PM* Suspend weekend MITSIS Grad Appointment feed.|
|F|M|F|1319223580105| |donovan@mit.edu|*Friday, 12/2/2011, By 5:00 PM* Workflow and JV Validation Reports.|
|F|M|F|1319223616512| |donovan@mit.edu|*Friday, 12/2/2011, 4:35 PM* Stop EDI Production Jobs.|
|F|M|F|1319223669901| |donovan@mit.edu|*Friday, 12/2/2011, 5 PM* Shut down EDI application server.|
|F|M|F|1319223710646| |donovan@mit.edu|*Friday, 12/2/2011, 5 PM* Voice message update when system goes down.|
|F|M|F|1319223793064| |donovan@mit.edu|*Friday, 12/2/2011, 5 PM* System Downtime Message (3-Down)|
|F|M|F|1319223847388| |donovan@mit.edu|*Friday, 12/2/2011, 5 PM* Bring down application servers. Production Environment becomes unavailable.|
|F|M|F|1319223885200| |donovan@mit.edu|*Friday, 12/2/2011, 5 PM* Disable Gateways.|
|F|M|F|1319223920100| |donovan@mit.edu|*Friday, 12/2/2011, 5 PM* Suspend Drop-box processing.|
|F|M|F|1319223968742| |donovan@mit.edu|*Friday, 12/2/2011, 5-7 PM* Validation Reports (Trial Balance) executed in SAP.|
|F|M|F|1319224072443| |donovan@mit.edu|*Friday, 12/2/2011, 5-7 PM* Limited activity in PS1.|
|
| Tasklist | ||||||
|---|---|---|---|---|---|---|
| ||||||
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1319225412229| |donovan@mit.edu|*Friday, 12/2/2011, 7-10 PM* Backup PS1.|
|F|M|F|1319225511778| |donovan@mit.edu|*Friday, 12/2/2011 - Saturday, 12/3/2011, 10 PM - 12 PM (Noon)* SAP ERP: Execute support pack application.|
|F|M|F|1319225582130| |donovan@mit.edu|*Saturday, 12/3/2011, 1-5 PM* Backup System.|
|F|M|F|1319225613975| |donovan@mit.edu|*Saturday, 12/3/2011, By 3 PM* Upgraded GuiXT scripts moved to Facilities Production Server.|
|F|M|F|1319225644733| |donovan@mit.edu|*Saturday, 12/3/2011, 4 PM* _Conference Call Check-in - use webex line_.|
|F|M|F|1319225673088| |donovan@mit.edu|*Saturday, 12/3/2011, 5-10 PM* Execute Oracle DB Upgrade.|
|F|M|F|1319225713182| |donovan@mit.edu|*Saturday, 12/3/2011 - Sunday, 12/4/2011, 10 PM - 2 AM* Backup System.|
|F|M|F|1319225765763| |donovan@mit.edu|*Saturday, 12/3/2011 - Sunday,12/4/2011, 10 PM - 8 AM* Generate DB Statistics; Complete ABAP loads.|
|F|M|F|1319225832017| |donovan@mit.edu|*Sunday, 12/4/2011, 3-5 AM* Transports Application.|
|
| Tasklist | ||||||
|---|---|---|---|---|---|---|
| ||||||
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1319224799246| |donovan@mit.edu|*Sunday, 12/4/2011, 8 AM* Validation reports executed (trial balance reports).|
|F|M|F|1319224847250| |donovan@mit.edu|*Sunday, 12/4/2011, 10 AM* Unlock web-services ids in Production.|
|F|M|F|1321631357748| |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* Enable Gateways (SAPWeb/ESS).|
|F|M|F|1321631478081| |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* EDI Step 1: Update SAP EDI Version number.|
|F|M|F|1319224915007| |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* EDI Step 2: Turn on the EDI 'gourmet-1' server.|
|F|M|F|1319224958553| |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* EDI Step 3: Schedule EDI job.|
|F|M|F|1319225905482| |donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* Email to ist-sap@mit.edu.|
|F|M|F|1319226000923| |donovan@mit.edu|*Sunday, 12/4/2011, 11 AM* R3-Admin Action Log.|
|F|M|F|1319226039994| |donovan@mit.edu|*Sunday, 12/4/2011, 12 PM - 2 PM* ADMIN SYS Action log tasks.|
|F|M|F|1319226077530| |donovan@mit.edu|*Sunday, 12/4/2011, By 2 PM* Update voice message whether Data Validation is on schedule.|
|F|M|F|1319226107914| |donovan@mit.edu|*Sunday, 12/4/2011, By 2 PM* Unlock testers.|
|F|M|F|1319226164776| |donovan@mit.edu|*Sunday, 12/4/2011, 2-4 PM* PS1 Data Validations & Transaction processing.|
|F|M|F|1319226219506| |donovan@mit.edu|*Sunday, 12/4/2011, By 4 PM* Coordinators for each area should send email to sap-validation-team@mit.edu at the completion of the validation notifying results.|
|F|M|F|1319226270713| |donovan@mit.edu|*Sunday, 12/4/2011, 4 PM* _Conference Call Check-in Go/No-Go decision - use webex line_.|
|F|M|F|1319226312531| |donovan@mit.edu|*Sunday, 12/4/2011, after conference call* send email notifying results.|
|F|M|F|1319226379715| |donovan@mit.edu|*Sunday, 12/4/2011, 8 PM - 12 AM* Data Warehouse Job Validation.|
|F|M|F|1319226413580| |donovan@mit.edu|*Sunday, 12/4/2011, 8-10 PM* Unlock users.|
|F|M|F|1319226433006| |donovan@mit.edu|*Sunday, 12/4/2011, 10 PM* Enable Dropbox.|
|F|M|F|1319226463541| |donovan@mit.edu|*Sunday, 12/4/2011, 10 PM* Execute ProCard from Bank of America feed.|
|F|M|F|1319226494960| |donovan@mit.edu|*Monday, 12/5/2011, 1:30 AM* On Line back up of PS1.|
|F|M|F|1319226926024| |donovan@mit.edu|*Monday, 12/5/2011, By 6AM* Update 3-down web page & SAPgui message.|
|F|M|F|1319226958132| |donovan@mit.edu|*Monday, 12/5/2011, By 6 AM* Remove SAPweb, ESS and EHS messages.|
|F|M|F|1319227009224| |donovan@mit.edu|*Monday, 12/5/2011, 6 AM* Email notification to MIT community stating update complete and production available.|
|F|M|F|1319227037379| |donovan@mit.edu|*Monday, 12/5/2011, 9 AM* Reinstate weekend MITSIS Grad Appointment feed.|
|