Pre-Update Schedule and Processes
Pre-Update Schedule and Processes
width80%
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|T|M|F|1321629489192|1322536057377|fquern@mit.edu|*By Sunday, 11/27/2011 8 AM* Download Basis notes for the PS1 required for the upgrade|
|F|M|F|1321629574243|          |donovan@mit.edu|*Sunday, 11/27/2011, 8 AM* DSM Upgrade & associated notes.|
|T|M|F|1321629654586|1322536041275|fquern@mit.edu|*Sunday, 11/27/2011 10 AM* Begin online upgrade piece of the application of Enhancement Pack(s)|
|T|M|F|1319222115555|          |donovan@mit.edu|*Monday, 11/28/2011, by 9 AM*  Post messages on insideMIT, SAPweb and ESS Web sites of upcoming SAP outage.|
|T|M|F|1319222167545|1322522110279|jad@mit.edu|*(2) Monday 11/28/2011, 12 PM*  Send message to MIT-SAP community about upcoming SAP outage.|
|T|M|F|1319222216395|1322535902776|fquern@mit.edu|*(3) Monday, 11/28/2011, 12 PM*  Post message on SAPgui indicating upcoming SAP outage.|
|F|M|F|1319222262777|          |donovan@mit.edu|*Tuesday, 11/29/2011, 11 AM*  IS&T - Cutover weekend planning meeting.|
|F|M|F|1319222474613|          |donovan@mit.edu|*Wednesday, 11/30/2011, 10 AM-12 PM*  SAP upgrade Core/Action log team meeting - review Cutover schedule and details.|
|F|M|F|1319222530271|          |donovan@mit.edu|*Wednesday, 11/30/2011, 1 PM*  Steering Committee, review test result, Go/No-Go decision.|
|F|M|F|1319222316994|          |donovan@mit.edu|*Thursday, 12/1/2011. 12 PM*  Steering Committee Meeting - review cutover plan.|
|F|M|F|1319222748441|          |donovan@mit.edu|Thursday, 12/1/2011, 1 PM  Email Steering Committee Go/No-go decision.|
|F|M|F|1319222941825|          |donovan@mit.edu|*Thursday, 12/1/2011, 2-3 PM*  Final review - RT issues, transport list, web components.|
|F|M|F|1319223014696|          |donovan@mit.edu|*Thursday, 12/1/2011, By 4 PM*  Schedule Pre & Post Trail balance reports.|
|F|M|F|1319223055588|          |donovan@mit.edu|*Thursday, 12/1/2011, By 4 PM*  R3-Admin email nessage about system down time.|
|F|M|F|1319223115685|          |donovan@mit.edu|*Thursday, 12/1/2011, By 4 PM*  Final copy of Production Update Schedule published and emailed.|
|F|M|F|1319223207714|          |donovan@mit.edu|*Friday, 12/2/2011, By 12 PM (Noon)*  Facility Supervisors print out work lists as back up for Monday morning.|
|F|M|F|1319223270013|          |donovan@mit.edu|*Friday, 12/2/2011, By 12 PM (Noon)*  Reschedule (shift) DW batch jobs to Sunday night.|
|F|M|F|1319223309453|          |donovan@mit.edu|*Friday, 12/2/2011, By 4:30 PM*  Suspend weekend MITSIS Grad Appointment feed.|
|F|M|F|1319223580105|          |donovan@mit.edu|*Friday, 12/2/2011, By 5:00 PM*  Workflow and JV Validation Reports.|
|F|M|F|1319223616512|          |donovan@mit.edu|*Friday, 12/2/2011, 4:35 PM*  Stop EDI Production Jobs.|
|F|M|F|1319223669901|          |donovan@mit.edu|*Friday, 12/2/2011, 5 PM*  Shut down EDI application server.|
|F|M|F|1319223710646|          |donovan@mit.edu|*Friday, 12/2/2011, 5 PM*  Voice message update when system goes down.|
|F|M|F|1319223793064|          |donovan@mit.edu|*Friday, 12/2/2011, 5 PM*  System Downtime Message (3-Down)|
|F|M|F|1319223847388|          |donovan@mit.edu|*Friday, 12/2/2011, 5 PM*  Bring down application servers.  Production Environment becomes unavailable.|
|F|M|F|1319223885200|          |donovan@mit.edu|*Friday, 12/2/2011, 5 PM*  Disable Gateways.|
|F|M|F|1319223920100|          |donovan@mit.edu|*Friday, 12/2/2011, 5 PM*  Suspend Drop-box processing.|
|F|M|F|1319223968742|          |donovan@mit.edu|*Friday, 12/2/2011, 5-7 PM*  Validation Reports (Trial Balance) executed in SAP.|
|F|M|F|1319224072443|          |donovan@mit.edu|*Friday, 12/2/2011, 5-7 PM*  Limited activity in PS1.|

...