Comment: Dynamic Task List: Task status changed in list 'SP Preparation Tasks and Processes (11/26 - 11/30)'

...

Tasklist
SP Preparation Tasks and Processes (11/26 - 11/30)
SP Preparation Tasks and Processes (11/26 - 11/30)
width120
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|T|M|F|1353992245091|1353992431360|fquern@mit.edu|1. Monday by 9am - Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage.|
|T|M|F|1353992401356|1353992820746|fquern@mit.edu|2. Monday by 10am - Post message on ECAT web site about upcoming SAP outage.|
|F|M|F|1353992489296|          |fquern@mit.edu|3. Monday 10am - Begin online upgrade piece of the application of Enhancement Pack(s)|
|T|M|F|1353992810926|1353992823977|fquern@mit.edu|4. Monday 12pm - Post message on SAPgui indicating upcoming SAP outage|
|T|M|F|1353992909394|1353993013590|fquern@mit.edu|5. Monday by 5pm - Confirm that there are no GuiXT Changes|
|T|M|F|1353992987753|1353993015014|fquern@mit.edu|6. Monday by 5pm - Send message to MIT-SAP community about upcoming SAP outage.|
|F|M|F|1353993328028|          |fquern@mit.edu|7. Tuesday 10:30am - Cutover weekend planning meeting IS&T.|
|FT|M|F|1353993394048|          1354053783087|fquern@mit.edu|8. Tuesday 12pm - Steering Committee Meeting – review cut-over plan/ Go/No-go decision – W92|
|T|M|F|1353993513572|1354053781072|fquern@mit.edu|9. Tuesday by 5pm - Email Steering Committee Go/No-go decision|