SP Application and Processes (11/30 - 12/1)
SP Application and Processes (11/30 - 12/1)
width120
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1354203478268|          |donovan@mit.edu|30. Friday 7:00pm - 12:00am - Backup PS1.|
|F|M|F|1354203507846|          |donovan@mit.edu|31. Saturday 12am - 9am - SAP ERP: Execute support pack application; includes BSI upgrade.|
|F|M|F|1354203540814|          |donovan@mit.edu|32. Saturday 9am-1pm - Backup System (R-MAN)|
|F|M|F|1354203585046|          |donovan@mit.edu|33. Saturday 1pm - 9pm - Execute concurrently: Generate DB Statistics (6 – 8 hours) Complete ABAP Loads (5 hours)|
Tasklist
width120
titleSP Post Upgrade Schedule and Processes (12/2 - 12/3)

...