Tasklist
SP Post Upgrade Schedule and Processes (12/2 - 12/3)
SP Post Upgrade Schedule and Processes (12/2 - 12/3)
width120
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1354203762956|          |donovan@mit.edu|39. Sunday 1:30am - 7:00am - On Line back up of PS1 (reestablishment of SRDF mirroring).|
|F|M|F|1354204893716|          |donovan@mit.edu|40. Sunday 8-9am - TB Validation reports validated|
|F|M|F|1354204915323|          |donovan@mit.edu|41. Sunday 8-10am - R3-Admin Action Log|
|F|M|F|1354204938588|          |donovan@mit.edu|42. Sunday 8am - Unlock web-services ids in Production|
|F|M|F|1354204970698|          |donovan@mit.edu|43. Sunday 8am - Enable Gateways (SAPWeb/ESS); after verifying application connections.|
|F|M|F|1354204989814|          |donovan@mit.edu|44. Sunday by 10am - Execute SAP report SEGREP to update segment length in the table EDISDEF|
|F|M|F|1354205023408|          |donovan@mit.edu|45. Sunday by 10am - EDI Step 1 Turn on the EDI “gourmet-1” server (start EDI)|
|F|M|F|1354205045615|          |donovan@mit.edu|46. Sunday by 10am - EDI (TLE) Step 2a Update SAP EDI Version number|
|F|M|F|1354205067597|          |donovan@mit.edu|47. Sunday 10am - EDI (TLE) Step 2b Load new BEN mappings (TLE)|