| Tasklist | ||||||
|---|---|---|---|---|---|---|
| ||||||
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1354203762956| |donovan@mit.edu|39. Sunday 1:30am - 7:00am - On Line back up of PS1 (reestablishment of SRDF mirroring).|
|F|M|F|1354204893716| |donovan@mit.edu|40. Sunday 8-9am - TB Validation reports validated|
|F|M|F|1354204915323| |donovan@mit.edu|41. Sunday 8-10am - R3-Admin Action Log|
|F|M|F|1354204938588| |donovan@mit.edu|42. Sunday 8am - Unlock web-services ids in Production|
|F|M|F|1354204970698| |donovan@mit.edu|43. Sunday 8am - Enable Gateways (SAPWeb/ESS); after verifying application connections.|
|F|M|F|1354204989814| |donovan@mit.edu|44. Sunday by 10am - Execute SAP report SEGREP to update segment length in the table EDISDEF|
|F|M|F|1354205023408| |donovan@mit.edu|45. Sunday by 10am - EDI Step 1 Turn on the EDI “gourmet-1” server (start EDI)|
|F|M|F|1354205045615| |donovan@mit.edu|46. Sunday by 10am - EDI (TLE) Step 2a Update SAP EDI Version number|
|F|M|F|1354205067597| |donovan@mit.edu|47. Sunday 10am - EDI (TLE) Step 2b Load new BEN mappings (TLE)|
|F|M|F|1354205106876| |donovan@mit.edu|48. Sunday 10:30am - EDI Step 3 Start EDI Jobs|
|F|M|F|1354205142962| |donovan@mit.edu|49. Sunday by 11am - EDI Step 4 (last step) Schedule EDI Job|
|F|M|F|1354205173023| |donovan@mit.edu|50. Sunday by 10am - Email to ist-sap@mit.edu • List of transports applied and any related issues. • List of jobs shifted in PS1 during cutover|
|F|M|F|1354205228396| |donovan@mit.edu|51. Sunday 10am - 12pm - • ADMIN SYS Action Log users unlocked • ADMIN SYS executes the PS1 Action Log / Validations and email steps completed to rest of the team (sap-action-log-team@mit.edu) • ADMIN SYS Extended Team reviews transport logs|
|F|M|F|1354205264813| |donovan@mit.edu|52. Sunday by 12 Noon - Unlock validators (testers)|
|F|M|F|1354205287133| |donovan@mit.edu|53. Sunday by 12 Noon - Update voice message whether or not Data Validation is on schedule.|
|F|M|F|1354205338674| |donovan@mit.edu|54. Sunday 12pm - 2pm - PS1 Data Validations & Transaction processing|
|F|M|F|1354205364701| |donovan@mit.edu|55. Sunday by 2pm - Coordinators for each area should send email to sap-validation-team@mit.edu at the completion of validations indicating any issues encountered.|
|F|M|F|1354205390238| |donovan@mit.edu|56. Sunday 2:30pm - Conference Call Check-in Go/No Go conference call Sunday webex Line|
|F|M|F|1354205447309| |donovan@mit.edu|57. Sunday after conference call - Send e-mail to (sapbiz, sap-upgrade-core, ist-sap@mit.edu,warehouse@mit.edu, Elena@mit.edu,) indicating decisions/results.|
|F|M|F|1354205482249| |donovan@mit.edu|58. Sunday 3pm-5pm - Unlock users (Facilities, SMART) Unlock all users (R3-Admin notifies operations center at 3-1500).|
|F|M|F|1354205501150| |donovan@mit.edu|59. Sunday 5pm - Enable Drop box|
|F|M|F|1354205531024| |donovan@mit.edu|60. Sunday by 5pm - Execute ProCard from Bank of America Feed|
|F|M|F|1354205562985| |donovan@mit.edu|61. Sunday 8pm-12am - Data Warehouse Job Validation|
|F|M|F|1354205593792| |donovan@mit.edu|62. Monday 1:30am - On Line back up of PS1 (reestablishment of SRDF mirroring).|
|