Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Dynamic Task List: Task status changed in list 'SP Application and Processes (11/30 - 12/1)'

...

Tasklist
SP Application and Processes (11/30 - 12/1)
SP Application and Processes (11/30 - 12/1)
width120
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|T|M|F|1354203478268|1354376729915|fquern@mit.edu|30. Friday 7:00pm - 12:00am - Backup PS1.|
|T|M|F|1354203507846|1354392521248|fquern@mit.edu|31. Saturday 12am - 9am - SAP ERP: Execute support pack application; includes BSI upgrade.|
|FT|M|F|1354203540814|          |donovan@mit1354417257939|fquern@mit.edu|32. Saturday 9am-1pm - Backup System (R-MAN)|
|F|M|F|1354203585046|          |donovan@mit.edu|33. Saturday 1pm - 9pm - Execute concurrently: Generate DB Statistics (6 – 8 hours) Complete ABAP Loads (5 hours)|
|T|M|F|1354203614905|1354399794040|fquern@mit.edu|34. Saturday 4pm - Conference Call Check-in Core Team Check in at 4pm on Saturday (use conference call webex line)|
|F|M|F|1354203638673|          |donovan@mit.edu|35. Saturday 9pm - Restore WT Table (once loads are done)|
|F|M|F|1354203663787|          |donovan@mit.edu|36. Saturday 9pm-10pm - Transports Application – after the completion of the ABAP Loads|
|F|M|F|1354203688883|          |donovan@mit.edu|37. Saturday 10pm - Set Production Flag for Finance|
|F|M|F|1354203717363|          |donovan@mit.edu|38. Saturday 10:30pm - Validation reports executed (trial balance reports)|

...