  • review outline for ITSM tool implementation vendor proposals
  • review and prioritize new product requests
  • update of service request queue
  • virtualization clause for Ts&Cs draft for December/January
  • vendor contacts overdue (Finance)
    • Pat followed up with Paul and Allen 11/7
    • Pat will meet with them again 12/5
  • licensing "red flag" language due from Finance end November
  • Pipeline list as page in KB
    • can publish as email
    • include last week completed in internal email
  • discussion regarding community facing webpage for Pipeline
    • ITSM tool as vehicle
    • improve how we deploy and convey information
    • how do we connect to 3Down?
  • any interest in sponsoring fix to 3Down feed to IS&T Website?
    • 3Down as it stands may not be priority
    • ITSM tool could be replacement
    • need new process
    • Garry will look into (as of January 2013)

December 2012

Release Core did not meet in person as all meeting time was dedicated to the ITSM Project.

January 22, 2013

  • schedule meeting with Finance (Pat):
    • migrating data from FM DB to portfolio prototype
      • Dave and Steve to check drupal content types for correct relationships prior to any migration
    • review renewal cycle
      • prioritize renewals
      • virtualization Ts&Cs
      • meet with VPF Procurement
  • add Service Release Checklist to KB Library of Procedures (Pat)
    • possible pilot review with Frank Q and/or Bill K?
  • review latest version of Product Release Checklist (Dave)
  • Endnote not a priority - see VSLS wiki: