FinalizedRoll Out Strategy For New Service Offerings

Reviewed next steps:

  • Chris Murphy will initiate demonstration (Step 4 of roll out) to be scheduled for Network Operations and Windows Infrastructure staff for end February
  • Core Remedy team (Garry, Chris Gresham, Dave Soble and Pat) will review current configurations, roles and asset information in preparation for on boarding additional services 2/25
  • Sponsor meeting 2/27
  • Tim will initiate demonstration (Step 4) to be scheduled for Merchant Services for first week of March
  • Pat will initiate demonstration (Step 4) to be scheduled for RAFT early March (after their next sprint)

February 4, 2013

Initial meeting to discuss scope and candidates for Remedy Change Management roll out.

...