High-Level Timeline

...

(tick) Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production

...

10/

...

dd/

...

13 – SAP release of year end base level support pack

...

10/

...

dd/

...

2013 – Production outage; DB & OS upgrade

...

10/

...

dd/2012 - End of day production snapshot to be used to refresh test environments
(tick) 10/22/2012 - Development Freeze begins

...