| Wiki Markup |
|---|
h4. Presentations {attachments}
h4. Meeting Notes
----
*{+} |
| Attachments |
|---|
12/3/2010 - |
...
Agenda
SAPbiz{+}* *Agenda* * *Project Update* * *SIT Update* * *Review of Cutover Plan*\\ *{+}11/1/2010 - SP Steering |
...
Committee{+}* In attendence: Bart Dahlstom, Frank Quern, Gerry O'Toole, John Doyle, Marty Dugal, Steve Buckley, Bill VanSchalkwyk, Mary Weiss, Magdalene Lee, Kathleen Flynn (standing in for Wayne Turner) |
...
Please see Steering Committee presentation attached above (dated 11/1/2010). |
...
Agenda
Agenda * Updates * Where are we now? * Project Risks (update) * Important Dates * Next Steps *{+}11/1/2010 - Core Team |
...
Meeting{+}* In attendence: core team members |
...
Updates
...
Updates * System Preparation ** SFK update complete ** SF3 update *** Mods complete (several will be applied through enhancement in SF2) *** Should be able to move forward and execute Payroll Simulation & DW test extracts *** Plan on executing go-live validation steps in SF3 11/2-11/3 |
...
*** Preliminary times: kernel - 1hr, SPS - 12hr, Oracle Upgade - 8hr) |
...
*** lost a day in the process due to a back up failure |
...
** SF2 update started |
...
*** action log on Wednesday |
...
*** R3 will change ZUTTREQ target system to SH3 (no change to ZUTTREQ should be required) |
...
*** Unit testing is scheduled to begin Thursday |
...
** SH3 refresh starting this week |
...
*** portal from SF5 will be used for SH3 |
...
...
...
10/25/2010 - Core Team Meeting
In attendence: core team members
Updates
10/19/2010 - Core Team Meeting
In attendence: core team members
Updates
10/12/2010 - Core Team Meeting
In attendence: core team members
Updates
10/04/2010 - SP Steering Committee
In attendence: Bart Dahlstom, Frank Quern, Gerry O'Toole, John Doyle, Marty Dugal, Kevin Lyons (standing in for Steve Buckley), Wayne Turner, Bill VanSchalkwyk
Please see Steering Committee presentation attached above (dated 10/04/2010).
Agenda
10/04/2010 - Core Team Meeting
In attendence: core team members
Updates
The SIT window is 11/11/2010 – 12/10/2010 but there are restrictions around this.
11/11/2010 is a holiday but HRP will begin the payroll comparison runs on this day.
The first 5 business days, 11/11/2010 through 11/17/2010, are reserved for the execution of payroll comparison runs (weekly, monthly & pension).
11/18/2010 is reserved for a controlled Financial Close.
11/19/2010 through 12/5/2010 is open for the general SIT testing (your full pool of testers – business & is&t); please note that there are two holidays embedded in this period (Thanksgiving 11/25-26).
12/6/2010 will be reserved for a controlled Financial Close.
12/7/2010 through 12/8/2010 is reserved for retesting outstanding issues.
12/9/2010 is reserved to execute the validation test in SH3 that will be performed in PS1 on go-live weekend.
12/10/2010 - go live weekend!** Business users meetings status - all areas have or have had meetings scheduled
09/27/2010 - Core Team Meeting
Agenda
09/22/2010 - SAPbiz Meeting
Presentation of the project, please see attachment above.
09/20/2010 - Core Team Meeting
In attendence: core team members
Updates
09/13/2010 - Core Team Meeting
In attendence: core team members
Agenda
09/09/2010 - IS&T Kickoff Meeting
In attendence: ist-sap list members
Agenda
Meeting presentation is attached above.
09/07/2010 - SP Steering Committee
In attendence: Bart Dahlstom, Frank Quern, Gerry O'Toole, John Doyle, Magdalene Lee, Mary Weiss, Steve Buckley, Wayne Turner
Agenda
Meeting's presentation is attached above.
...
* Testing ** Plans published on the wiki ** Unit test plan *** need to develop spreadsheet upload of new transactions changes to the unit test db *** set up meeting with Rich, Ken, Mary, Frank - determine how to track unit test activity ** SIT test plan - confirm with Business; make sure testers areaware of what and when they are testing ** QC queries have been developed * Development freeze is underway * Broad deactivation will move in with normal transports this week * GUI logon development work will begin this week ** change will be tested in SF7 ** moved to SF2 (rebuilt) on the weekend and tested with Mon-Wed test transactions * John will create transport list November 12 (we'll need to determine what will be done with transports in test that have not moved to production) * Need to set up a bridgeline for Core meeting going forward *{+}10/25/2010 - Core Team Meeting{+}* In attendence: core team members Updates * System Preparation ** SFK update near completion ** SF3 update starting *** Mods planned for Thursday *** ABAP team needs to be available * Testing ** Will publish plan on the wiki (new page will be developed) ** Unit test plan - near completion *** need to develop spreadsheet upload of new transactions changes to the unit test db ** SIT test plan - near completion as well ** QC queries underdevelopment * Development freeze is one week away \\ *{+}10/19/2010 - Core Team Meeting{+}* In attendence: core team members Updates * System Preparation ** SF3 has been refreshed; refreshed action log execution on schedule ** SF3 payroll simulation run on schedule ** SF7 practice system still being built (missing a patch level) *** this system will be used to develop gui logon changes ** Support Pack side effects report has been generated and posted to the Project Scope page of this wiki ** SFK Support Pack Application process has begun ** Support Application process will begin in SF3 starting next Monday * Test Planning ** Unit Test *** for the most part 2009/2010 comparisons are complete *** new transaction review is in process *** Rich is working on additional query requests (though off-site this week) ** SIT *** needs to be wrapped up by 10/25 *** Actively in progress ** Goal is to communicate test plans at SAPbiz * Transport management ** Updated list is has been posted on the wiki ** Many of the transports on the list are obsolete ** Several projects are going live this week so the list will significantly drop down *{+}10/12/2010 - Core Team Meeting{+}* In attendence: core team members Updates * System Preparation ** SF3 is now off line and being refreshed in preparation of Support Pack Application ** SF8 is now the system for the application of OSS notes for production support ** Request to review Action Log ** SF7 being used as a practice system and the system for Logon development work * Test Planning ** Unit test planning *** In progress - extended due date to 10/15 *** "Z" drive mapping needed for access to unit test db (see Rich for access) *** Reporting needed **** matrix report **** list of what's being tested for publication ** SIT test planning *** Extended due date to 10/25 *** Basic structures have been agreed to *** User groups have been shown QC *** Automated test cases need to be validated/modified for HRP (in-progress) *** HRP waiting on EL cases ** Goal is to publish test plan at 10/27 SAPbiz meeting ** QC license restriction becoming a concern again (turns out we do not have unlimited view access) * SAP SP release scheduled for 10/14 is on track/Application scheduled to begin in SFK on Monday 10/18 \\ *{+}10/04/2010 - SP Steering Committee{+}* In attendence: Bart Dahlstom, Frank Quern, Gerry O'Toole, John Doyle, Marty Dugal, Kevin Lyons (standing in for Steve Buckley), Wayne Turner, Bill VanSchalkwyk Please see Steering Committee presentation attached above (dated 10/04/2010). Agenda * Updates * Where are we now? * Project Risks (update) * Important Dates * Next Steps \\ *{+}10/04/2010 - Core Team Meeting{+}* In attendence: core team members Updates * Test Planning ** Review Dates ** SF3 will not be initally scrambled to accomodate a simulation run of the monthly payroll ** Production validation steps will be executed in SF3 ** SIT (more detailed date view): The SIT window is 11/11/2010 -- 12/10/2010 but there are restrictions around this. 11/11/2010 is a holiday but HRP will begin the payroll comparison runs on this day. The first 5 business days, 11/11/2010 through 11/17/2010, are reserved for the execution of payroll comparison runs (weekly, monthly & pension). 11/18/2010 is reserved for a controlled Financial Close. 11/19/2010 through 12/5/2010 is open for the general SIT testing (your full pool of testers -- business & is&t); please note that there are two holidays embedded in this period (Thanksgiving 11/25-26). 12/6/2010 will be reserved for a controlled Financial Close. \\ 12/7/2010 through 12/8/2010 is reserved for retesting outstanding issues. 12/9/2010 is reserved to execute the validation test in SH3 that will be performed in PS1 on go-live weekend. 12/10/2010 - go live weekend\!*\* Business users meetings status - all areas have or have had meetings scheduled * Unit test db - ready for use by test coordinators * System preparation ** SF7 will be used for (1) a practice system and (2) source system for GUI user exit updates ** Ancillary system updates *** Solution manager (SPS24 - complete through production) *** Portal target SPS7 *** PI w/ ADS target SPS7 ** PS1 snapshot scheduled for tonight (10/04/2010) to be used to refresh SF3 * QC ** HRP domain has been set up ** Additional licenses have been installed ** File attachment issues have been resolved ** Need to load in production validations steps * Risks Update ** EL went live\! ** eW2 moved forward to 10/21 ** OE still scheduled for 10/21 ** New project Remove MIT Alert from SAP (end of October) ** Broad Deactivation been identified (could go before the freeze) ** Unicode - obsolete programs may move with the Support Packs * Transports ** Core team to review and report strategy for transports by 10/8 to Transport Coordinator (John Tuttle) *{+}09/27/2010 \- Core Team Meeting{+}* Agenda * QC Updates ** License issues ** HRP Domain * System Prep Updates * Unit test DB * Test Planning Updates * Transport Strategies (begin next week) ** updated list will be created on Friday (10/1) \\ *{+}09/22/2010 \- SAPbiz Meeting{+}* Presentation of the project, please see attachment above. \\ *{+}09/20/2010 - Core Team Meeting{+}* In attendence: core team members Updates * Project scope ** NW EHP 2 will not be available until December 2010 therefore it is nolonger in the scope of this project ** Confirmed that HRP SP 27 is the base level required for year end tax reporting and will be released by SAP on 10/14/2010 ** Solution manager needs to updated to stack 24 has a prerequisite for the application of this years support packs (update is in progress) * Quality Center ** additional five licences have not been installed (should be by weeks end) ** problem creating a secure domain for HRP test scripts; issue has been opened up with SAP * Unit test catalog DB ** development uderway; should be complete by week's end * Other ** practice system identified: SF7 ** test planning has started (meetings have been scheduled w/ BOs) ** will post project related email lists on the wiki \\ *{+}09/13/2010 - Core Team Meeting{+}* In attendence: core team members Agenda * Set schedule date and time for core team meetings ** consensus to meet Monday's at 10:00-11:00am for the duration of the project; location W92:Downtown Crossing * Review of detail project plan ** discussion around practice system ** discussion around transports ** discussion around testing ** discussion around freeze * Next steps ** focus on test plan ** confirm NW 7.0 EHP 2 availability & compatibility (Bart & Ron are pursuing with SAP) ** focus on moving current development work to production ** SAPbiz meeting on 9/22/2010 *{+}09/09/2010 - IS&T Kickoff Meeting{+}* In attendence: ist-sap list members Agenda * Background * Project Organization * Project wiki * Project Risks * Important Dates * Next Steps Meeting presentation is attached above. \\ *{+}09/07/2010 - SP Steering Committee{+}* In attendence: Bart Dahlstom, Frank Quern, Gerry O'Toole, John Doyle, Magdalene Lee, Mary Weiss, Steve Buckley, Wayne Turner Agenda * Background * Project Scope * Project Organization * High Level Time Line * Project Risks * Roles & Responsibilities * Important Dates * Next Steps Meeting's presentation is attached above. The general consensus is to move forward with the project as planned. |