Support Pack Project
Key Dates
- Now - October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
- 10/18/2010 - End of day production snapshot to be used to refresh test environments (a)
- 11/01/2010 - Development Freeze begins
- 11/09/2010 - Last date to implement support & enhancement changes until freeze ends on 12/15/2010
- 11/04/2010 - 11/10/2010 Unit test
- 11/11/2010 - 12/10/2010 System Integration Test (b)
- 12/10/2010 - 12/12/2010 Go-live weekend
- 12/15/2010 - Development Freeze ends
High Level Project Schedule
2010 SP High Level Schedule.png
Monthly Priorities & Deliverables
Month | Major Deliverables | Responsible |
|---|
September | - Plan project, resources, kickoff
- QA instructions, templates
- Update test scripts, catalog
- Move pending work to production
| - Frank Quern
- Wendy Bastos
- QA Team, Functional Test Coordinators
- Extended Functional Teams
|
October | - System preparation
- Continue moving pending work to production
- Complete test plan
| - Technical Core Team
- Extended Functional Teams
- QA, Functional Test Coordinators
|
November | - Unit test
- Start SIT
| - Extended functional team members
- Extended Functional Team, Business Owners
|
December | - Complete SIT
- SP applied to Production
| - Extended Function Team, Business Owners
- All
|
Detailed Project Plan
SAP SP 2010_Project_Plan.mpp
Page Notes
(a) The 10/18/2010 snapshot date is being used because it stages time data after its load and before evaluation, it right before the monthly and pension pay runs, it is relatively close to the freeze date minimizing the number of transports that will need to be imported into the test environment before execution of the SP application process.
(b) SIT & UAT phases will be combined as one process this year.