High-Level Timeline
...
Now (Sept) thru the end of October - Plan, convert/create/update test scripts in ALM/QC, move pending support & project work into production

...
10/
...
09/
...
2014 - SAP release of year end base level support pack
10/
...
20/
...
2014 - End of day production snapshot to be used to refresh test environments
10/
...
20/
...
2014 - Development Freeze begins

...
10/
...
28/
...
2014 - Last date to implement support & enhancement changes until freeze ends on 12/
...
10/
...
2014
10/
...
24/
...
2014 -
...
Unit test

...
11/
...
03/
...
2014 -
...
System Integration Test (regression test fixes: 11/25-26
...
/
...
2014)
12/
...
05/
...
2014 -
...
Go-live weekend!
...
12/
...
10/
...
2014 - Development Freeze ends