High-Level Timeline
...

...
September thru the end of October - Plan, convert/create/update test scripts in ALM
...
, move pending support & project work into production

...
10/
...
13/
...
2016 - SAP release of year end base level support pack

...
10/
...
13/
...
2016 - Last date to implement support & enhancement changes until freeze ends on 12/07/2016
10/
...
15/
...
2016 - Development Freeze begins

...
10/
...
17/
...
2016 - End of day production snapshot to be used to refresh test environments (9/19 for SF3)
10/24/2016 - Unit test
11/
...
01/
...
2016 - System Integration Test (regression test fixes: 11/
...
22-
...
23/
...
2016)
...
12/
...
02/
...
2016 - Go-live weekend!
...
12/07/2016 - Development Freeze ends