High-Level Timeline

...
September thru the end of October - Plan,
...
create/update test scripts in ALM, move pending support & project work into production.

...
10/
...
12/
...
2017 - SAP release of year end base level support pack

...
10/
...
19/
...
2017 - Last date to implement support & enhancement changes until freeze ends on 12/
...
13/
...
2017

...
10/
...
20/
...
2017 - Development Freeze begins
10/
...
23/
...
2017 - End of day production snapshot to be used to refresh test environments (9/
...
25 for SF3)
10/
...
25/
...
2017 - Unit test
11/
...
02/2017 - 11/03/2017 Controlled Payroll Runs (SH2)
11/06/2017 - System Integration Test (regression test fixes: 11/
...
29-
...
30/
...
2017)
...
12/
...
08/
...
2017 - Go-live weekend! (start Friday at 5pm)
12/
...
13/
...
2017 - Development Freeze ends