High-Level Timeline

(tick)

...

 Now and thru the end of October -
              Plan, create/update test scripts in ALM, move pending support & project work into production.
(tick) 10/

...

11/

...

2018 - SAP release of year end base level support pack
(tick) 10/

...

18/

...

2018 - Last date to implement support & enhancement changes until freeze ends on 12/

...

12/

...

2018
(tick) 10/

...

19/

...

2018 - Development Freeze begins
(tick) 10/

...

22/

...

2018 - End of day production snapshot to be used to refresh test environments (9/

...

17 for SF3)
(tick) 10/

...

24/

...

2018 - Unit test

(tick) 11/0201/2017 2018 - 11/0302/2017 2018 Controlled Payroll Runs (SH2)

(tick) 11/

...

05/

...

2018 - System Integration Test (regression test fixes: 11/29-30/

...

2018)

...

(info) 12/

...

07/

...

2018 - Go-live weekend! (start Friday at 5pm)

(info) 12/

...

12/

...

2018 - Development Freeze ends