Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

High-Level Timeline

By end-of-day Nov

...

3 - Plan, create/update test scripts in ALM. (SAP Business Areas)
End of day production snapshot from 9/

...

18/

...

2023 to be used to refresh SF3 environment
End of day production snapshot from 9/

...

26/

...

2023 to be used to refresh SH1 environment
End of day production snapshot from 10/

...

16/

...

2023 to be used to refresh SH2 environment

Refer to calendar for detailed time frames

2022 2023 SAP Support Pack Upgrade - Calendar View

Oct

...

5: SAP releases year-end support pack versions
Oct

...

13-

...

18: SF3 upgrade
Oct

...

16:  SH1 ready for use
Oct

...

20 at 5PM: start of SF2 restricted window
Oct 21-24

...

: SF2 upgrade
Oct

...

24 at 5PM: start of SH2 restricted window
Oct

...

25-

...

Oct 31: SH2 refresh and upgrade
Nov 2-3

...

: IS&T Controlled Payroll Test
Nov

...

6-

...

28: SH2 business testing
Nov

...

29 -Dec

...

1 - Uptime Production Cut-over Activities -
Dec

...

1-Dec

...

3 - Go-live weekend! (start Friday at 5pm)
Dec

...

4 - Upgraded  PS1 is ready for use


---------


SAP Scheduled Upgrades - Ancillary Systems

ERP (systems SF3, SF2, SH2, PS1):

-- EHP8 for SAP ERP 6.0 SPS 19 w/21 with HR SP 01110124 (a.k.a. B1) (systems SF3, SF2, SH2, PS1)C4)

---- SAP KERNEL 7.53 54 64-BIT UNICODE PL 1035200

---- SMERP  630_740  SP 00100012

---- SMFND  630_740  SP 00100012

 

NetWeaver ADS (systems DSD, DST, DSP):

-- NetWeaver 750 SPS 25 28 with SAP JVM 8.1.090095 (or higher)

 

NetWeaver/GRC :-- NetWeaver/GRC (systems ACD, ACT, ACP):

---- SAP KERNEL 7.53 54 64-BIT UNICODE PL 1000200

---- NetWeaver 7.52 SPS 11 13 (estimated to be available by October 28th16th)

---- GRC Access Control 12.0 SPS 1822

 

SAP Business Technology Platform (formerly SCP) HANA DB:

-- HANA 2.00.059.04 09 or higher

 

SAP Mobile (TBD):   Work Manager recently upgraded on 10/12/2022.  Confirming timing on Inventory Manager upgrade (Facilities Stockroom) :   N/A for 2023

 

Ancillary Systems:  IAAS applications

BSI, SFTP, OpenText  -  BSI (OS and Server in scope); SFTP (not in scope);  OpenText (HANA DB update, DB OS in scope | App Server OS and migration not in scope).  

Details below on schedule:

OTP (OpenText IaaS server) Disk Scale Up 10/07 Done (expedited maintenance)

PS1 (ERP Prod DB server) Physical to Virtual Migration 10/07 Done

ACD (NetWeaver/GRC) Application Software Update  10/16 17:00 -> 10/18 01:00

 

DSD (NetWeaver/ADS) Database Software Update 10/17 Done

DSD (NetWeaver/ADS) Application Software Update 10/17 15:00 -> 10/18 22:00

 

HAN (OpenText Non-Prod DB server) Operating System Update  10/23 18:00 -> 20:30

 

DST (NetWeaver/ADS) Database Software Update 10/24 18:30 -> 21:30

 

HAN (OpenText Non-Prod DB server) Database Software Update 10/26 18:00 -> 22:00

 

DSP (NetWeaver/ADS) Database Software Update 11/04 01:45 -> 05:45

HAP (OpenText Prod DB server) Operating System Update  11/04 01:45 -> 04:30

PS1 (ERP Prod DB server) Database Software Update 11/04 01:45 -> 05:30

 

HAP (OpenText Prod DB server) Database Software Update 12/02 03:00 -> 08:00

 

DST (NetWeaver/ADS) Application Software TBD

DST (NetWeaver/ADS) Application Software TBD

ACT (NetWeaver/GRC) Application Software Update  TBD

ACP (NetWeaver/GRC) Application Software Update  TBD

 

Note: 

The OpenText DB server maintenance is independent of the OpenText IaaS migrations to new SLES 15.4 servers, which are considered out of scope.