Directors, Platform Engagement, IS&T, MIT
| - Provide oversight, schedule resources
- Define roles & responsibilities
- Set standards, guidelines, processes, metrics
- Remove obstacles, resolve issues
- Approve go/no go decision
|
Project Manager | Kevin Lyons, MIT | - Complete project on time, on budget
- Manage overall project: plan, track progress, resolve issues, escalate when necessary
- Communicate: with project team, sponsors, steering committee, stakeholders, broader community
- Ensure appropriate business and IS&T resources are assigned to project tasks
- Coordinate work among project teams, data warehouse, OIS, IS&T help desk, ...
|
Transport Coordinator | Elda Prudden | - Define process, lists, tracking procedures
- Plan and track effort to move pending transports to production before freeze
- Manage any critical transports during freeze to ensure they are included in upgrade
- Manage all transports related to support pack project
|
Core Team: Technical Leads | R3 Administration Team Infrastructure Team Lead - Ron Parker | - Prepare environments
- Apply support packs related to support pack project * Execute SF3 modification testing; Resolve & retest issues
- Unit test (joint with functional team)
- Analyze & resolve issues
- Execute cut-over activities
- Coordinate work of basis team and developers
|
Core Team: Functional Leads | - HRP (HR/Payroll) PO - Frank Quern
- Benefits
- Compensation
- Human Resources (Service Center)
- Payroll
- Pension Payroll
- Enterprise Learning
- FLE (AP/FI/PO) PO - Bob Casey
- Financial Operations (AP, Merchant Services, Procurement Operations,
Travel
|