High-Level Timeline
...
August thru the end of October - Plan,
...
create/update test scripts in ALM/QC, move pending support & project work into production
...
10/
...
02/2015 -
...
Development Freeze begins
10/
...
05/2015 - End of day production snapshot to be used to refresh test environments
...
10/
...
08/2015 -
...
SAP release of year end base level support pack
10/15
...
/2015 - Last date to implement support & enhancement changes until freeze ends on 12/16/2015
...
10/
...
19/2015 - Unit test
...
10/
...
29/2015 - System Integration Test (10/29-30 controlled pay runs; regression test fixes: 11/24-25/2015)
11/25 – Mock Cut-over/Disaster Recover Test (cycle 5/6)

12/11/2015 - Go-live weekend!
...