Process
| Status/Current Risks | Attachments
|
---|
Prepare Initiate
| - 0-budget project limits product selection
- buy-in from other teams to use their systems as proof-of-concept still pending
| Project Startup Checklist TBD: Sponsor Checklist
|
Prepare
| - Scope deliverable complete but milestone planning still insufficient
| Project Scope
|
- Cost/Benefit is anecdotal, based on team background and experience, increases to efficiency unmeasured going into the project.
- Scope complete, out-of-scope definition requires refinement
| Daptiv Project Profile
|
Planning and Resource Allocation
| - End date still undetermined, planning still in process.
- SAIS is still considering participation in the project and timeframe for participation.
| Project Resource Plan Daptiv Project Home Business Requirements |
Track and Control
| TBD: QA Checklist
|
| - Task and milestone estimates rough, completion dates arbitrary
- Risks need better defintion
| Task List PDF Export Daptiv Tasks and Milestones Daptiv Risks
|
Reporting
|
| Project Snapshot Measurements of Installation Efficiency Reporting
|
Review
|
|
|
Completion and Assessment
|
|
|