High-Level Timeline

...

(tick)

...

September thru the end of October - Plan, convert/create/update test scripts in ALM, move pending support & project work into production
(tick) 10/13/2016 - SAP release of year end base level support pack

...

(tick) 10/17/2016 - End of day production snapshot to be used to refresh test environments (9/19 for SF3)
(tick) 10/24/2016 - Unit test
(plus)(tick) 11/01/2016 - System Integration Test (regression test fixes: 11/22-23/2016)

...