Project cut-over status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/4/2020 through noon on Monday 12/7/2020. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
| Friday Sunday December 4 46 3:30PM: Pre-isolation activities are in progressSupport Pack is complete. All production systems are back online |
|---|
...