Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
10/10/2013 – SAP release of year end base level support pack
...
10/
...
10/21/2013 - End of day production snapshot to be used to refresh test environments
10/19/2013 - Development Freeze begins
...
10/
...
31/2013 - Last date to implement support & enhancement changes until freeze ends on 12/
...
11/2013
10/25/2013 - 11/01/2013 Unit test
...
11/04/2013 -
...
12/
...
02/2013 System Integration Test (regression test fixes:
...
11/26-27 & 12/2)
12/7/2013 - 12/8/2013 Go-live weekend!
...
12/
...
11/2013 - Development Freeze ends