High-Level Timeline

(plus)(tick) September thru the end of October - Plan, create/update test scripts in ALM, move pending support & project work into production.
(green star)(tick) 10/12/2017 - SAP release of year end base level support pack

...

(tick) 10/23/2017 - End of day production snapshot to be used to refresh test environments (9/25 for SF3)
(info)(tick) 10/25/2017 - Unit test

(info) 11(tick) 11/02/2017 - 11/03/2017 Controlled Payroll Runs (SH2)

(info)(tick) 11/06/2017 - System Integration Test (regression test fixes: 11/29-30/2017)

(warning)(tick) 12/08/2017 - Go-live weekend! (start Friday at 5pm)

...