High-Level Timeline

...

(tick) August

...

thru the end of October - Plan,

...

create/update test scripts in ALM/QC, move pending support & project work into production
(info) (tick) 10/02/2015 - Development Freeze begins
(tick) 10/05/2015 - End of day production snapshot to be used to refresh test environments
(tick) (info) 10/08/2015 - SAP release of year end base level support pack
(info) 10(tick) 10/15/2015 - Last date to implement support & enhancement changes until freeze ends on 12/16/2015

...

(tick) 10/19/2015 -

...

Unit test
(info) 10/23/2015 - Unit test

...

(tick) 10/29/2015 -

System Integration Test (10/29-30 controlled pay runs; regression test fixes: 11/24-25/2015)

(tick) 11/25 – Mock Cut-over/Disaster Recover Test (cycle 5/6)

(info)(green star) 12/11/2015 - Go-live weekend!

...