High-Level Timeline

(plus)(tick) September thru the end of October - Plan, create/update test scripts in ALM, move pending support & project work into production.

...

(tick) 11/02/2017 - 11/03/2017 Controlled Payroll Runs (SH2)

(plus)(tick) 11/06/2017 - System Integration Test (regression test fixes: 11/29-30/2017)

(warning)(tick) 12/08/2017 - Go-live weekend! (start Friday at 5pm)

...