Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migrated to Confluence 4.0

...

Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
(question) (tick) 10/10/2013 – SAP release of year end base level support pack

...

(tick) 10/

...

(question) 10/21/2013 - End of day production snapshot to be used to refresh test environments
(question) (tick) 10/19/2013 - Development Freeze begins
(question) (tick) 10/31/2013 - Last date to implement support & enhancement changes until freeze ends on 12/11/2013
(question) (tick) 10/25/2013 - 11/01/2013 Unit test

...

(tick) 11/04/2013 - 12/

...

02/2013 System Integration Test (regression test fixes: 11/26-27 & 12/

...

2)

(question) (tick) 12/7/2013 - 12/8/2013 Go-live weekend!

(question) (info) 12/11/2013 - Development Freeze ends