Note:
...
Go-live weekend 12/2-12/5.
Cutover plan
...
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F| | |donovan@mit.edu|Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage|
|F|M|F|1319039659578| |donovan@mit.edu|Send message to MIT-SAP community about upcoming SAP outage. (message at end of plan)|
| Tasklist |
|---|
| title | Support Pack Application and Processes |
|---|
|
Update Firewall to restrict acces to SAP gateway; send confirmation to R3-Admin when complete, cc fquern@mit.edu |
| Tasklist |
|---|
| title | Post Upgrade Schedule and Processes |
|---|
|
Validation reports executed (trial balance reports).
* R3-ADMIN notifies Becky Reeves via email with a copy to Frank Quern (fquern@mit.edu) as soon as the trial balance is available for review.
*R3-ADMIN unlocks BREEVES id in PS1.
* Becky notifies Frank Quern (fquern@mit.edu) when validation of trial balance report is complete.
|
...