Cut-over Plan Detail

Cut-over Plan Check List

Cutover plan

...


||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|          |          |donovan@mit.edu|Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage|
|F|M|F|1319039659578|          |donovan@mit.edu|Send message to MIT-SAP community about upcoming SAP outage.  (message at end of plan)|
Tasklist
titleSupport Pack Application and Processes
Update Firewall to restrict acces to SAP gateway; send confirmation to R3-Admin when complete, cc fquern@mit.edu
Tasklist
titlePost Upgrade Schedule and Processes
Validation reports executed (trial balance reports).
 * R3-ADMIN notifies Becky Reeves via email with a copy to Frank Quern (fquern@mit.edu) as soon as the trial balance is available for review.
 *R3-ADMIN unlocks BREEVES id in PS1.
 * Becky notifies Frank Quern (fquern@mit.edu) when validation of trial balance report is complete.

...