Oct 16 5PM - SF2 restricted development mode starts - complete
Oct 17 - Nov 1: Automated Testing SF3 -

...

complete
Oct 17 - Oct 18 - Unit test  SF3 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 21 - Oct 25 - Unit test  SF2 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) -

...

complete
Oct

...

29- Oct

...

30 -  Controlled Payroll Run Test  - (IS&T HR and EpiUse Support Team) - Complete
Oct

...

29 - Nov

...

13- System Integration Test  (Central Office Business Teams) - complete
Oct

...

29 - VPF test to compare year-to-date tax information with production - complete
Nov

...

14 - Nov

...

15 - Bug fixes and regression testing (Central Office Business Teams, IS&T and EpiUse) - complete
Nov

...

18 - Nov

...

22 - Uptime Production Cut-over Activities - in progress

Nov

...

22 - Nov

...

24 - Go-live weekend! (start Friday at 5pm)

Nov

...

25 - Upgraded  PS1 is ready for use

---------

SAP Scheduled Upgrades - Ancillary Systems

...