2021 2022 Final Post Upgrade Transport List
Project cutover status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/32/2021 2022 through noon on Monday 12/65/20212022. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
| Sun Sunday 12/ 504/ 21 1:30PM: SAP Production Support Pack upgrade is complete. Production environment is available22 2:30 PM: Support pack upgrade and system validations are completed |
|---|
...