The following is a copy of the Support Pack Cut-over and Test Plans:

2022 2023 SAP Support Pack Cutover Plan

2022 2023 FLE Validations

2022 2023 HRP PS1 Business Validations.xlsx

2022 2023 PS1 User List

2022 2023 Final Post Upgrade Transport List  

Communication

Project cutover status of the upgrade, see below,  will be posted on this wiki page beginning at noon on Friday 12/21/2022 2023 through noon on Monday 12/54/20222023.  The Project Manager will update this message as needed.  A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.

Project Status: 

Friday 10Sunday 12/273/23 4:00 PM:   Updates on the cutover weekend (Dec 1-3, 2023) coming soon2023 3:30PM:  SAP Support Pack update is complete.  PS1 is available to the MIT Community.

Conference Calls (Zoom) for cut-over weekend:

  • Saturday 4:30PM IS&T 
  • Sunday 1PM Validation review

Office Excel
name2022 2023 SP - Cutover Plan.xlsx