Final IST Service Portfolio Scope.doc
PS Release Processes Phase II Project Plan v 2.0.xlsx

Service Portfolio Time Line (Revised)

...

  • release checklist completed
  • draft processes and roles as to how Service Portfolio gets and Catalog get updated
  • target date: May 15th

...

  • reference sources gathered
  • tasks:
    • define information architecture
    • identify vehicle (technology)
    • data entry
    • reconciliation with Service Catalog
    • identify orphans
  • target date: June 1st

...

  • process maps completed
  • user stories completed
  • tasks:
    • define set of procedures to standardize
    • criteria:
      • capacity/efficiency
      • cost savings
      • improved communication (transparency)
      • easy to achieve
    • possible candidates for Phase I:
      • distributed software acquisition
      • triage (problem/response)
      • retirement of a service
      • updating portfolioPortfolio and Catalog
  • target date: April 1st

Deliverable G: Implementation

  • tasks:
    • roll out plan
    • feedback loop for improvements
  • target dates: June 1st through August 15th

Next meeting Thursday, January 13th at 10am in W92 Fenway.

Proposed agenda:

  • quick recap of Sponsor meeting January 10th
  • review requirements
  • make decisions on:
    • information architecture
    • vehicle for portfolio
    • procedures to be defined