March 5, 2013
- MSA must replace MSSA (will need legal review by MIT)
- dates will now be pushed out to 4/15-6/15/13
- still waiting for dev performanace language to be worked into SoW or SLA (for minimum of 3 months after prototype go live)
- check in on 3/8/13 with BMC as to status
March 1, 2013
- proposal is still being worked on by BMC and will be delayed until 3/4/13
- performance of dev environment is still an issue
- Bryan will send proposal of "guarantees" for review
February 27, 2013
- BMC will push dates to 3/25 to 6/7/13
- Dave to reschedule webex
- Reference card in progress
- performance language being worked on by BMC legal
- CV language limited to consultants on site and that we would interact directly with
- Analytics license language included (we may want to think about adding it to July renewal if we really like it)
- BMC to provide additional clauses from MSA for inclusion in MSSA we signed previously
- Next draft due COB Friday 3/1 from BMC
- Check in meeting scheduled for Tuesday 3/5 at 1pm
February 25, 2013
BMC still working on amendments to version two of the document: MIT SOW 22022013-RoD_FINAL.pdf
- Reference card as to time and cost savings for future implementations
- Bio/CV language that info provided upon execution of contract and subject to MIT IS&T approval
- Analytics trial license to be included as part of prototype
- Reference original MSSA as opposed to attached MSA
- Resolution of performance issues in development environment as part of contract
- Dave will participate in webex session on 2/26 to replicate performance issues
- Pat drafted following for BMC: Dev Performance Resolution Language
PDF name As part of this scope of work.pdf - Dave will participate in webex session on 2/26 to replicate performance issues
February 15, 2012
BMC has agreed to the following next steps in terms of amendments to the draft SOW (attached) to be delivered by 2/20: MIT GOLD SOW-V3 1 23012013-ProjectBased V2.21.docx
...