Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
(tick) 10/

...

10/

...

2013 – SAP release of year end base level support pack
(tick) 10/

...

21/2013

...

- End of day production snapshot to be used to refresh test environments
(tick) 10/

...

19/

...

2013 - Development Freeze begins
(tick)

...

10/

...

31/

...

2013 - Last date to implement support & enhancement changes until freeze ends on 12/

...

11/

...

2013
(tick) 10/

...

25/

...

2013 - 11/

...

01/

...

2013 Unit test

(tick) 11/

...

04/

...

2013 -

...

12/

...

02/

...

2013 System Integration Test

...

(regression test fixes: 11/26-27 & 12/2)

(tick) 12/

...

7/

...

2013 - 12/

...

8/

...

2013 Go-live weekend!

...

(info) 12/

...

11/

...

2013 - Development Freeze ends