Oct 16 5PM - SF2 restricted development mode starts - complete
Oct 17 - Nov 1: Automated Testing SF3 -
...
complete
Oct 17 - Oct 18 - Unit test SF3 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 21 - Oct 25 - Unit test SF2 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 29- Oct 30 - Controlled Payroll Run Test - (IS&T HR and EpiUse Support Team) - Complete
Oct 29 - Nov 13- System Integration Test (Central Office Business Teams) - complete
Oct 29 - VPF test to compare year-to-date tax information with production - complete
Nov 14 - Nov 15 - Bug fixes and regression testing (Central Office Business Teams, IS&T and EpiUse) - complete
Nov 18 - Nov 22 - Uptime Production Cut-over Activities - in progress
Nov 22 - Nov 24 - Go-live weekend! (start Friday at 5pm)
...