High-Level Timeline

(info) Now (tick) Now and thru the end of October -
              Plan, create/update test scripts in ALM, move pending support & project work into production.
(info)(tick) 10/11/2018 - SAP release of year end base level support pack
(info)(tick) 10/18/2018 - Last date to implement support & enhancement changes until freeze ends on 12/12/2018
(info)(tick) 10/19/2018 - Development Freeze begins

...

(tick) 10/22/2018 - End of day production snapshot to be used to refresh test environments (9/

...

17 for SF3)
(info)(tick) 10/24/2018 - Unit test

(info)(tick) 11/01/2018 - 11/02/2018 Controlled Payroll Runs (SH2)

(info)(tick) 11/05/2018 - System Integration Test (regression test fixes: 11/29-30/2018)

...