Thalia Roadmap
  

Sprint phase:

Sprint 5 6a - Release eng: Robin

Next Sprint 6b - Release eng: ?

 sprint planning preparation

 sprint planning meeting

  •  product product owner picks focus, features, and bugs for next sprint, moves to a new sprint bucket in JIRA
  • all: may nominate candidate bugs and features for sprint

 

 

  • all: look at sprint bucket in JIRA and make estimates for their tasks
  • release engineer chosen

2/11

 

  • all: separate design and implementation for new features when entering issues in jira
  • Product Owner prioritizes items for planned work.
  • sprint planning meeting:
    • Choices for planned work are reviewed by team
    • Release engineer chosen
    • Required design meetings are identified and planned/scheduled

3/21 - 3/27
planning meeting: 3/27

3/21 - 3/27
(one planning for all of sprint 6)

development and design cycle sprint begins

  • dev: starts coding on clearly defined features
  • dev: facilitates required design meetings, and documents final design choices so QA can prepare test plans, know what to expect with new features
  • qa: starts testplans
  • scrum master: produces burndown chart
  • ongoing releases to test environment as needed, to be negotiated between dev and QA

2/12

 

  • New features / planned work first;
  • Last week of cycle is for bug backlog

3/31 - 4/11

4/11 - 5/23
* will overlap with bug fixing for sprint 6a

first release to qa  new features/planned work completed

  • release engineer or dev: releases to QA machine
  • dev: code is branched, and all new development occurs in a that sprint's branch
  • dev: if there is time before issues related to immediate build come in, start starts bugfixes from backlog
  • QA: test plans complete, testing  of planned work begins

3/11


4/22

5/26

iterative qa phase bugfixes from backlog completed

  • dev:  start work on bugfixes for planned work
  • qa: verifies backlog fixes, and fixes as specified in each version's release notes
  • customer relations: sends an early notification to thalia-info

3/18

 

final bugfixes completed

  • dev: all new development occurs in a new branch
  • qa: verifies final bugfixes 

3/??

 

4/22 - 5/1

5/26 - 6/13

QA makes recommendation about release -- team decides go/no go for proposed production release date QA gives green light to release

  • qa: all fixes verified, no blockers
  • customer relations: sends an immanent imminent release announcement to thalia-info 24-48 hours before release
  • release engineer: 24 hours before release, notify server ops of service outage

3 5/24 1

  6/13

release to production

  • release engineer and ops: release code - release window is a Tuesday or Wednesday, 6PM-9PM
  • release engineer: send confirmation to server ops that release was successful
  • customer relations: send confirmation to thalia-info that release was successful

3/25 or 3/26

 

5/6

6/17


---------------  

Post sprint organization...

...

Sprint Number

Dev Freeze Date

Code Freeze

Release Date

Release Engineer

1

September 21, 2007

October 12

October 15/16

Robin

2

October 29, 2007

November 1

November 5

Janet

3

December 3, 2007

December 10

December 13/14

Qing

4

January 4, 2008 everything except access control
January 11, 2008 code freeze

Jan 25, 2008

Jan 29, 2008

Janet

5

March 11 2008 dev code freeze

March 18, 2008
Arnis sent out the customer announcement

March 25, 26, 2008
Arnis sent out the service outage note the day before the release
and reiterate the major features in this release

Robin Qing


Pre-sprint organization

Oct 2 Usability test

...