Oct 29- Oct 30 -  Controlled Payroll Run Test  - (IS&T HR and EpiUse Support Team) - Complete
Oct 29 - Nov 13- System Integration Test  (Central Office Business Teams) -

...

complete
Oct 29 - VPF test to compare year-to-date tax information with production - complete
Nov 14 - Nov 15 - Bug fixes and regression testing (Central Office Business Teams, IS&T and EpiUse) - complete
Nov 18 - Nov 22 - Uptime Production Cut-over Activities - in progress

Nov 22 - Nov 24 - Go-live weekend! (start Friday at 5pm)

...