Project cutover status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/1/2023 through noon on Monday 12/4/2023. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
Saturday Sunday 12/23/2023 83:45AM30PM: On Track. Technical Post Upgrade Processing by R3-Admin in progressSAP Support Pack update is complete. PS1 is available to the MIT Community. |
|---|
...