2021 HRP Validations

2021 PS1 User List

2021 Final Post Upgrade Transport List

Communication

Project cut-over cutover status of the upgrade, see below,  will be posted on this wiki page beginning at noon on Friday 12/43/2020 2021 through noon on Monday 12/76/20202021.  The Project Manager will update this message as needed.  A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.

Project Status: 
Tuesday September 21: Support Pack planning activities in progressSun 12/5/21 1:30PM: SAP Production Support Pack upgrade is complete. Production environment is available

Conference Calls (Zoom) for cut-over weekend:

...