By end-of-day Nov 4 - Plan, create/update test scripts in ALM. (SAP Business Areas)
End of day production snapshot from 9/
...
19/
...
2022 to be used to refresh SF3
...
environment
End of day production snapshot from 9/27/2022 to be used to refresh SH1 environment
End of day production snapshot from 10/
...
17/
...
2022 to be used to refresh SH2
...
environment
Refer to calendar for detailed time frames
2022 2023 SAP Support Pack Upgrade - Calendar View
Oct 5: SAP releases year-end support pack versions
Oct
...
13-
...
18: SF3 upgrade
Oct 16: SH1 ready for use
Oct 22 at 5PM: start of SF2 restricted window
Oct 23-25
...
: SF2 upgrade
Oct
...
24 at 5PM: start of SH2 restricted window
Oct
...
25 -
...
Oct 31: SH2 refresh and upgrade
Nov
...
2-
...
3: IS&T Controlled Payroll Test
Nov
...
6-
...
28: SH2 business testing
Nov 29 -Dec 1 -
...
Uptime Production Cut-over Activities -
Dec
...
1-Dec
...
3 - Go-live weekend! (start Friday at 5pm)
Dec
...
4 - Upgraded PS1 is ready for use
---------
SAP Scheduled Upgrades - Ancillary Systems
ERP Target
ERP:
ERP:
-- EHP8 for SAP ERP 6.0 SPS 19 w/HR SP 0111(a.k.a. C4) (systems SF3, SF2, SH2, PS1)
---- SAP KERNEL 7.53 64-BIT UNICODE PL 1035
---- SMERP 630_740 SP 0010
---- SMFND 630_740 SP 0010
NetWeaver ADS:
-- NetWeaver 750 SPS 25 with SAP JVM 8.1.090
NetWeaver/GRC:
...
-- NetWeaver/GRC (systems ACD, ACT, ACP)
---- SAP KERNEL 7.53 64-BIT UNICODE PL 1000
---- NetWeaver 7.52 SPS 11 (estimated available by October 28th)
---- GRC Access Control 12.0 SPS 18
SAP Business Technology Platform (formerly SCP) HANA DB:
-- HANA 2.00.059.04 or higher
NetWeaver/ADS:
SAP Mobile (TBD): Work Manager recently upgraded on 10/12/2022. Confirming timing on Inventory Manager upgrade (Facilities Stockroom)