The last normal transports to Production will take place on Thursday, November 1, 2012. After that date, a freeze of non-critical transports to Production will be in effect until after the Support Pack Project Go Live date. The normal Production transport import schedule will resume on Thursday, December 6, 2012. Migrations to the Test environments (SH2SH1 - PreSP QA) and Production will be limited to critical fixes that need to be moved to Production as soon as possible. During the freeze, a special transport procedure will be enforced for changes to SAP. This section explains the approval process. It lists the necessary approvals and documentation, and what steps you need to take in ZUTTREQ. Questions about this process should be directed to John TuttleCarolyn Fuller, Transport Coordinator at jrtuttle@mit, at fuller@mit.edu (mailto: fuller@mit.edu) or 617-324253-00976213.
...
For the duration of the development freeze (10/2422/20112012-12/75/20112012), a special development process should be used for development of fixes to SAP. The aim of this process is to avoid the introduction of non-support pack changes into the Support Pack test system (SH1SH2) or the Production system (PS1).
The following are the steps in the special development process. Questions about this process should be directed to John TuttleCarolyn Fuller, Transport Coordinator at jrtuttle@mitfuller@mit.edu (mailto: fuller@mit.edu) or 617-324253-00976213.
...
All transports must be associated with a Request Tracker (RT) ticket recorded in the RT SAP::Test Issue queue under the project name 'SAP Support Pack 20112012'. Note: Any in-process changes saved during step 1 will need to be manually merged into the corrected objects after the development freeze.
...
What to do in ZUTTREQ:
Select SH1 SH2 as the 'To' environment. The ZUTTREQ program will send the request to Frank Quern for approval.
After he has given his approval, Ron the R3 Admin team (r3-chmgt@mit.edu) will move the transport(s) to SH1SH2 twice a day (shortly after 12 noon and then again after 5pm).
Transports generated during Unit Testing will be accumulated and moved as a group as part of the Support Pack application process in the test system, SH1SH2.
Transports generated during SIT will be imported into SH1 SH2 twice a day (shortly after 12 noon and then again after 5pm). Requests must be received by 11:30am and 4:30pm, respectively.
These transports must be associated with RT tickets recorded in the Request Tracker SAP::Test Issues queue under project name "SAP Support Pack 20112012".
Transport path = SF2 -> SH1SH2
Approver: Frank Quern
Before development is begun, it should be clear the business owner considers this change critical and requires an immediate fix. An email message describing the situation must be sent to Frank Quern (fquern@mit.edu (mailto: fquern@mit.edu)), with a copy sent to John Tuttle (jtuttle@mitCarolyn Fuller (fuller@mit.edu (mailto: fuller@mit.edu)), to facilitate consideration of the critical fix. After review Frank will request approval to migrate the fix to Test from one of the business members of the Steering Committee.
Development will be performed in SF2 both before and after the support and enhancement packs have been applied. While the support and enhancement packs are being applied to SF2, SF2 will be unavailable for development. If an emergency arises during this period, SF8 will be used for development.
Transport path SF2 -> SH2 SH1 (& SH1 SH2 for regression testing)
Approvers to begin the development work:
The functional team must follow the standard QA Issue Resolution procedure, which includes the PEC and associated test cases or an SAP mini-spec and associated test case documents.
Approvers for importing transports to production:
...
All transports must be associated with a Request Tracker (RT) ticket recorded in the Functional Team's Support queue and within the RT SAP::Test Issue queue under the project name 'SAP Support Pack 20112012'. These transports must be double tested, once in the production support path (SF2-> SH2SH1) and then again in the Support Pack path (SF2-> SH1SH2), before the transport(s) can be imported into production.
...
...
What to do in ZUTTREQ:
Check 'Critical' and 'To' environment as SH2SH1. After approval, Ron will the R3 Admin team (r3-chmgt@mit.edu) will move the transport(s) to SH2SH1, and SH1SH2.
Enterprise Learning 2.0.
Hourly Student Appointments
APR 2.0 (HR Transactions)
None scheduled at this time.
On December 76, 2011 2012 SAP system SH1 SH2 will be opened for normal testing activities to all IS&T SAP support personnel and business owners. The normal QA rules (documents in the review folders, all business owner approvals captured, RT tickets updated) will resume at that time as well. All changes approved on or after December 75, 2011 2012 will be considered part of the December 86, 2011 2012 transport cycle.