...
2011 Support_Pack_Cutover_Plan.docx
...
| Panel | |
|---|---|
Cut-over Plan DetailCut-over Plan Check List | |
| Tasklist | Support Pack Application and Processes | Support Pack Application and Processes |
| width | 80% |
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1319225412229| |donovan@mit.edu|*Friday, 12/2/2011, 7-10 PM* Backup PS1.|
|F|M|F|1319225511778| |donovan@mit.edu|*Friday 12/2/2011 - Saturday, 12/3/2011, 10 PM - 12 PM (Noon)* SAP ERP: Execute support pack application.|
|F|M|F|1319225582130| |donovan@mit.edu|*Saturday, 12/3/2011, 1-5 PM* Backup System.|
|F|M|F|1319225613975| |donovan@mit.edu|*Saturday, 12/3/2011, By 3 PM* Upgrade GuiXT scripts.|
|F|M|F|1319225644733| |donovan@mit.edu|*Saturday, 12/3/2011, 4 PM* _Conference Call Check-in - use webex line_.|
|F|M|F|1319225673088| |donovan@mit.edu|*Saturday, 12/3/2011, 5-10 PM* Execute Oracle SB Upgrade.|
|F|M|F|1319225713182| |donovan@mit.edu|*Saturday, 12/3/2011 - Sunday, 12/4/2011, 10 PM - 2 AM* Backup System.|
|F|M|F|1319225765763| |donovan@mit.edu|*Saturday, 12/3/2011 - Sunday,12/4/2011, 10 PM - 8 AM* Generate DB Statistics; Complete ABAP loads.|
|F|M|F|1319225832017| |donovan@mit.edu|*Sunday, 12/4/2011, 3-5 AM* Transports Application.|
| |
| Tasklist | |
| Post Upgrade Schedule and Processes | Post Upgrade Schedule and Processes |
| width | 80% |
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|T|M|F|1319224799246|1321631276370|donovan@mit.edu|*Sunday, 12/4/2011, 8 AM* Validation reports executed (trial balance reports).|
|T|M|F|1319224847250|1321631295555|donovan@mit.edu|*Sunday, 12/4/2011, 10 AM* Unlock web-services ids in Production.|
|T|M|F|1321631357748|1321631373902|donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* Enable Gateways (SAPWeb/ESS)|
|T|M|F|1321631478081|1321631531105|donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* EDI Step 1: Update SAP EDI Version number|
|T|M|F|1319224915007|1321631532028|donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* EDI Step 2: Turn on the EDI 'gourmet-1' server|
|T|M|F|1319224958553|1321631577397|donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* EDI Step 3: Schedule EDI job.|
|T|M|F|1319225905482|1321631601600|donovan@mit.edu|*Sunday, 12/4/2011, By 11 AM* Email to ist-sap@mit.edu.|
|T|M|F|1319226000923|1321631620346|donovan@mit.edu|*Sunday, 12/4/2011, 11 AM* R3-Admin Action Log.|
|T|M|F|1319226039994|1321631630463|donovan@mit.edu|*Sunday, 12/4/2011, 12 PM - 2 PM* ADMIN SYS Action log tasks.|
|T|M|F|1319226077530|1321631639711|donovan@mit.edu|*Sunday, 12/4/2011, By 2 PM* Update voice message whether Data Validation is on schedule.|
|T|M|F|1319226107914|1321631648288|donovan@mit.edu|*Sunday, 12/4/2011, By 2 PM* Unlock testers.|
|T|M|F|1319226164776|1321631652068|donovan@mit.edu|*Sunday, 12/4/2011, 2-4 PM* PS1 Data Validations & Transaction processing.|
|T|M|F|1319226219506|1321631715813|donovan@mit.edu|*Sunday, 12/4/2011, By 4 PM* Coordinators for each area should send email to sap-validation-team@mit.edu at the completion of the validation notifying results.|
|F|M|F|1319226270713| |donovan@mit.edu|*Sunday, 12/4/2011, 4 PM* _Conference Call Check-in Go/No-Go decision-use webex line_.|
|F|M|F|1319226312531| |donovan@mit.edu|*Sunday, 12/4/2011, after conference call* send email motifying results.|
|F|M|F|1319226379715| |donovan@mit.edu|*Sunday, 12/4/2011, 8 PM - 12 AM* Data Warehouse Job Validation.|
|F|M|F|1319226413580| |donovan@mit.edu|*Sunday, 12/4/2011, 8-10 PM* Unlock users.|
|F|M|F|1319226433006| |donovan@mit.edu|*Sunday, 12/4/2011, 10 PM* Enable Dropbox.|
|F|M|F|1319226463541| |donovan@mit.edu|*Sunday, 12/4/2011, 10 PM* Eecute ProCard from Bank of America feed.|
|F|M|F|1319226494960| |donovan@mit.edu|*Monday, 12/5/2011, 1:30 AM* On line back up of PS1.|
|F|M|F|1319226926024| |donovan@mit.edu|*Monday, 12/5/2011, By 6AM* Update 3-down web page & SAPgui message.|
|F|M|F|1319226958132| |donovan@mit.edu|*Monday, 12/5/2011, By 6 AM* Remove SAPweb, ESS And EHS messages.|
|F|M|F|1319227009224| |donovan@mit.edu|*Monday, 12/5/2011, 6 AM* Email notification to MIT community stating update complete and production available.|
|F|M|F|1319227037379| |donovan@mit.edu|*Monday, 12/5/2011, 9 AM* Reinstate weekend MITSIS Grad Appointment feed.|
|