High-Level Timeline
High-Level Timeline
...
August thru the end of October - Plan,
...
create/update test scripts in ALM/QC, move pending support & project work into production

...
10/
...
02/
...
2015 - Development Freeze begins
10/
...
05/
...
2015 - End of day production snapshot to be used to refresh test environments
10/
...
08/
...
2015 - SAP release of year end base level support pack
10/
...
15/
...
2015 - Last date to implement support & enhancement changes until freeze ends on 12/
...
16/
...
2015

...
10/
...
19/
...
2015 - Unit test

...
10/
...
29/
...
2015 - System Integration Test (10/29-30 controlled pay runs; regression test fixes: 11/24-25
...
/2015)
11/25 – Mock Cut-over/Disaster Recover Test (cycle 5/6)
12/11/2015
...
- Go-live weekend!
...
12/16/2015 - Development Freeze ends