Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Corrected links that should have been relative instead of absolute.

This folder contains current copies of relevant project schedules.  These schedules are attached in MSProject format an presented in HTML format.

High Level Plan for SAPBiz 10-822-08 v4 (last updated 14 Oct 2008)

----| Project Start:
Project Finish: | Project Start Date: Sat 9/20/08
Project Finish Date: Tue 12/23/08 |

...

Tasks

...

ID

 ID

Task _ Name

Duration

Start _Date

Finish _Date

Predecessors

Resournce Names

% Complete

  Resource_Names

1

2008 Support Pack Implementation Project

65 days

Mon 9/22/08

Tue 12/23/08

  

0%

2

Project Prep

33 30 days

Mon 9/22/08

Thu 11 Fri 10/631/08

  

0%

3

PS1 Snapshot at end of day

0 days

Mon 9/22/08

Mon 9/22/08

  

0%

4

Transaction list available

0 days

Fri 9/26/08

Fri 9/26/08

  R3 R3

0%

5

Identify test scenarios / transactions

5 days

Mon 9/29/08

Fri 10/3/08 4

BUS,BA

0%

6

Review and update test scripts

20 days

Mon 10/6/08

Fri 10/31/08

5

BUS,BA

0%

7

SF3 Unavailable at end of day

0 days

Fri 10/10/08

Fri 10/10/08

  

0%

8

PS1 snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

  R3 R3

0%

9

Execute Trial balance for snapshot

0.5 days

Mon 10/20/08

Mon 10/20/08

8 BUS BUS

0%

10

Save data warehouse extracts

0 days

Fri 10/10/08

Fri 10/10/08

7 DWH DWH

0%

11

Support packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

  

0%

12

PS1 Import 1

0 days

Thu 10/23/08

Thu 10/23/08

  

0%

13

PS1 Import 2

0 days

Thu 10/30/08

Thu 10/30/08

 

 

14

PS1 Import 3

0 days

Thu 11/6/08

Thu 11/6/08

 

 

15

SF3 System Refresh

5 days

Tue 10/14/08

Mon 10/20/08

  

0%

16 14

Refresh with 9/22/08 PS1 Snapshot

2 days

Tue 10/14/08

Wed 10/15/08

  R3 R3

0%

17 15

R3 Action Log

0.5 days

Thu 10/16/08

Thu 10/16/08 16

R3 R3

0%

18 16

Scramble sensitive data

2.5 days

Thu 10/16/08

Mon 10/20/08

17 R3 R3

0%

19 17

PS1 Snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

  

0%

20 18

Execute Trial Balance for later comparison

0.5 days

Mon 10/20/08

Mon 10/20/08

19 R3 R3

0%

21 19

Support Packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

  

0%

22 20

SFK Update

4 days

Tue 10/21/08

Fri 10/24/08

  

0%

23 21

Import Updates

1 day

Tue 10/21/08

Tue 10/21/08

21FS+1 day

R3

R3

0%

22 24

Identify and resolve import issues

1 day

Wed 10/22/08

Wed 10/22/08

23 R3 R3

0%

25 23

Validate security infrastructure (SNC)

1 day

Thu 10/23/08

Thu 10/23/08

24 R3 R3

0%

26 24

Validate SAPGui interactions

0.5 days

Fri 10/24/08

Fri 10/24/08

25 R3 R3

0%

27 25

Validate basic SAP functions work

0.5 days

Fri 10/24/08

Fri 10/24/08

R3

0%

26

PS1 Import - regular import cycle

0 days

Thu 10/23/08

Thu 10/23/08

 

0%

27

R3

28

SF3 Update

5 days

Mon 10/27/08

Fri 10/31/08

  

0%

29 28

Import Updates

2 days

Mon 10/27/08

Tue 10/28/08

21,27 R3 R3

0%

30 29

Execute action log

0.5 days

Wed 10/29/08

Wed 10/29/08 29

DEV,BA

0%

31 30

Update action log as necessary

0.5 days

Wed 10/29/08

Wed 10/29/08

 

DEV,BA

0%

31 32

Produce collision report

0.5 days

Wed 10/29/08

Wed 10/29/08 29

R3 R3

0%

33 32

Review collision report

1 day

Wed 10/29/08

Thu 10/30/08 32

DEV,BA

0%

33 34

Reimplement MIT mods

1 day

Thu 10/30/08

Fri 10/31/08

33 DEV DEV

0%

35 34

Confirm configuration steps work

0.5 days

Fri 10/31/08

Fri 10/31/08

34

DEV,BA

0%

35

Production Imports (last regular import cycle)

0 days

Thu 10/30/08

Thu 10/30/08

 

0%

36

Development slowdown starts

0 days

Fri 10/31/08

Fri 10/31/08

 

0%

37

Unit Test Preparation and Execution

6 days

Mon 11/3/08

Mon 11/10/08

  

0%

37 38

Apply support packs to SF2

2 days

Mon 11/3/08

Tue 11/4/08

35 R3 R3

0%

38 39

Update and Execute action log

0.5 days

Wed 11/5/08

Wed 11/5/08

37

BA,DEV

0%

40 39

Import transports from SF3

0.5 days

Wed 11/5/08

Wed 11/5/08

38 R3 R3

0%

40 41

Unit test, resolution and retest in SF2

3 days

Thu 11/6/08

Mon 11/10/08

39

BA,DEV

0%

41 42

System Test / User Acceptance Test Environment Preparations

10 days

Mon 10/27/08

Fri 11/7/08

  

0%

42 43

Refresh TST with 10/20 snapshot, NO SCRAMBLING DATA

3 days

Mon 10/27/08

Wed 10/29/08

  R3 R3

0%

43 44

Import post snapshot production transports (delta from 10/20 to 10/30)

2 days

Thu 10/30/08

Fri 10/31/08

42 R3 R3

0%

44 45

Import updates

2 days

Mon 11/3/08

Tue 11/4/08

43 R3 R3

0%

45 46

Import SF3 transports & post-update DEV transports (to be tested during SI & UAT)

1 day

Wed 11/5/08

Wed 11/5/08

44 DEV DEV

0%

46 47

Execute trial balance and compare with TB from 10/20

0.5 days

Thu 11/6/08

Thu 11/6/08

44,45 BUS BUS

0%

47 48

Execute action log

0.5 days

Thu 11/6/08

Thu 11/6/08

46

DEV,BA

0%

49 48

Execute DWH extracts and comparison

1 day

Fri 11/7/08

Fri 11/7/08

47

DWH

49

Development slowdown starts

0 days

Fri 11/7/08

Fri 11/7/08

48

 

0%

50

Execute System Integration Tests

6 days

Wed 11/12/08

Wed 11/19/08

  

0%

51

HR-Payroll

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

52

Logistics

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

53

EHS

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

54

Financial

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

0%

55

Execute User Acceptance Test (UAT)

15 days

Thu 11/20/08

Fri 12/12/08

  

0%

56

Payroll comparison (tasks and duration to be validated)

Execute UAT

9 3 days

Thu 11/20/08 Mon 11

Thu 12/244/08

54 BUS BA,BUS

0%

57 Execute

UAT Financial Close

7 2 days

Tue 11/25/08

Fri 12/5/08

56

BUS

58

Financial Close

1 day

Mon 12/8/08

Mon 12/8/08

BUS

0%

58

57

BUS

59

Issue retesting

2 days

Tue 12/9/08

Wed 12/10/08

58 ALL ALL

0%

60 59

Execute another financial close?

1 day

Thu 12/11/08

Thu 12/11/08

59 BUS BUS

0%

61 60

UAT sign off

1 day

Fri 12/12/08

Fri 12/12/08

60 ALL ALL

0%

62 61

Cutover weekend & Controlled Start

2 days

Sat 12/13/08

Sun 12/14/08

61 ALL ALL

0%

63 62

Drop Dead Date for support packs in production

0 days

Mon 12/22/08

Mon 12/22/08

  

0%

64 63

First Calendar 2009 Payroll

0 days

Tue 12/23/08

Tue 12/23/08

 

0%