||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F| | |donovan@mit.edu|Wednesday, 11/23/2011 by 9AM (5 minutes). Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage|
|F|M|F|1319039659578| |donovan@mit.edu|Send message to MIT-SAP community about upcoming SAP outage. (message at end of plan)|
...
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F| | |donovan@mit.edu|Update Firewall to restrict access to SAP gateway; send confirmation to R3-Admin when complete, cc fquern@mit.edu|
| Panel |
|---|
Cut-over Plan DetailCut-over Plan Check List |
...
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F| | | |Validation reports executed (trial balance reports). - R3-Admin notifies Becky Reeves via email with a copy to Frank Quern as soon as the trial balance report is complete. - R3-ADMIN unlocks BREEVES id in PS1. -Becky notifies Frank Quern when validation of Trial balance report is complete.|
...
| Item
| Date
| Time
| Action / Task
| Person(s)
Responsible
| Status
|
...
...
...
Pre-Update Schedule and Processes
...
...
...
1.
...
Thursday 12/2/2011
...
By 9 AM
(5 Minutes)
...
Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage.
(message can be found at end of this document)
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...
...