Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Role

Members

Primary Responsibilities

Communication

Sponsors

John Charles, VP IS&T, MIT

Anthony Sharon, Deputy Executive Vice President EVPT, MIT

Lorraine Goffe-Rush, VP HR, MIT

Glen Shor, VP Finance, MIT

Marianne Heer, Sr. VP SAP AmericaSponsor

 

  • Provide overall direction, goals & funding
  • Approve charter, scope, milestones, budget
  • Remove obstacles
  • Monthly written status report
  • Invitation to attend steering committee each month

Steering Committee

  • IS&T
  • Bill VanSchalkwyk (Managing Director, EHS Programs)
  • Kathleen Flynn (HR Manager of Operations)
  • Lisa St. Croix (Business Systems Manager, Department of Facilities)
  • Scott Ball (VPF, Business Systems Manager, Financial Systems and Data)
    Please refer to the SAPbiz Project Kick off document for the list while this page is under construction.
    • Provide oversight, schedule resources
    • Define roles & responsibilities
    • Set standards, guidelines, processes, metrics
    • Remove obstacles, resolve issues
    • Approve go/no go decision
    • Monthly steering committee meetings - October - January
    • September - TBD
    • October - TBD
    • November - TBD
    • December  Go/No Go decision
    • 1/2015 2016 (TBD) Post project review

    Project ManagerTBD

    Siobhan Cunningham, MIT

    Pat Casey, SAP

    • Complete project on time, on budget
    • Manage overall project: plan, track progress, resolve issues, escalate when necessary, ...
    • Communicate: with project team, sponsors, steering committee, stakeholders, broader community
    • Ensure appropriate business and IS&T resources are assigned to project tasks
    • Coordinate work among project teams, data warehouse, OIS, IS&T help desk, ...

     

    Transport CoordinatorTBD

    Eping (Lucia) Wei

    • Define process, lists, tracking procedures
    • Plan and track effort to move pending transports to production before freeze
    • Manage any critical transports during freeze to ensure they are included in upgrade
    • Manage all transports related to support pack project

     

    Core Team: Technical Leads

  • Basis/security - Ron Parker
  • Basis/authorizations - George Petrowsky
  • ABAP, ITS - Wai-Ming Li
  • Web - Kevin Mullins
  • DW - Scott ThorneR3 Administration Team
    • Prepare environments
    • Apply support packs related to support pack project * Execute SF3 modification testing; Resolve & retest issues
    • Unit test (joint with functional team)
    • Analyze & resolve issues
    • Execute cut-over activities
    • Coordinate work of basis team and developersWeekly core team meeting - Monday 1:00pm W92-Downtown Crossing starting
    • Daily Scrum PO Meetings
    • Kick off meeting 9/15TBD
    • sap-upgrade-core@mit.edu
    • project wiki

    Core Team: Functional Leads

    1. HRP (HR/Payroll) Testing Coordinator - Mary DonovanPO - Frank Quern
      1. Benefits
      2. Compensation
      3. Human Resources (Service Center)
      4. Payroll
      5. Pension Payroll
      6. Enterprise Learning
    2. FLE (AP/EHS/FI/PO) Testing Coordinator - Lee CollierPO - Bob Casey
      1. AP
      2. EHS
      3. Travel
      4. Procurement (xECAT3)
      5. Facilities
      6. FAR
      7. Parking
      8. ECAT3
      9. SMART (Singapore)
      Functional Team leadsFrank Quern (HRP)
    3. Atlas PO - Kevin Lyons
    4. System Architect
      1. Siobhan Cunnigham (FLE)
    5. Assistant Project Manager - Desiree Roberts
    • Unit testing (joint with technical team, track and report process)
    • System integration testing (define scope, update & execute scripts, track and report progress)
    • User acceptance testing (assist if needed)
    • Serve as primary liaison with business owners
    • Analyze & resolve issues
    • Execute cutover activities
    • Coordinate work of business analysis and business ownersWeekly core team meeting - Monday 1:00pm W92-Downtown Crossing starting 9/22
    • Kick off meeting 9/15 1:00pm
    • sap-upgrade-core@mit.edu
    • project wiki
    Core Team:
    • QA
    Debra Wiley
      • Define & communicate process & templates to manage test cases
      • Set standards for quality assurance process
      • Oversee QA work on the project
    • Weekly core team meeting - Monday 1:00pm W92-Downtown CrossingDaily Scrum PO Meetings
    • Kick off meeting 9/15TBD
    • sap-upgrade-core@mit.edu
    • project wiki

    Extended Team

    • ist-sap@mit.edu 
      • which includes all IS&T staff supporting SAP
      • Conact Frank Quern , Kevin Lyons or Bart Dahlstrom or Bob Casey if you are not on the list and think you should be
    • Perform tasks as directed by core team leads
    • Kick off meeting in September, before SAPbiz kickoff
    • ist-sap@mit.edu
    • project wiki

    Business Owners

    1. FAR, JV - Clarel AuGuste, Stephen Hoover
    2. HR/Payroll - Leslie Wright
    3. HR/Benefits - Michael Peretti, Diane Johnston
    4. Facilities - Lisa St. Croix
    5. Stockroom - Tammy Doyle
    6. EHS - Laurie Veal, Joe Macleod
    7. Spons. Billing - Timothy J Vacha, Dale C Twomey
    8. Gen AR - Donna Cairns
    9. Cashiers - Cheryl Whelan
    10. Property: Kevin J Milligan, Jo-Anne M Chute
    11. Fund Centers: Peggie McGrath
    12. IST Telecom: Allan Wallace
    13. Tech Review: Jim Coyle
    14. AP - John Larkin, Cathy Cherico
    15. Procurement - Sara Malconian (Scott Ball and Cindy Vye, BA)
    16. eCAT - Sara Malconian (Scott Ball and Cindy Vye, BA)
    17. Travel - Kathy McGrath (Cindy Vye, BA)
    18. SMART - Jay DellaPorta, John D Larkin, Elza Bilong, Sara Malconian, Long Tran
    19. OSP - Steve Dowdy
    20. OBO - Rob Slauzis
    21. Pcard - Kathy McGrath, Kim Harmon
    22. EL - Jane White, Melissa Kavlakli
    • Perform user acceptance testing (define scope, update & execute scripts, retest as needed)
    • Report issues via RT
    • Train end users if any changes are discovered (none anticipated)
    • Sign-off that updated system is accepted for your business area and support packs can move to production
    • Perform any business cut-over activities
    • Validate production system (define criteria, validate system)
    • Kick off meeting @  SAPbiz meeting
    • Every other week at SAPBiz or as required
    • Meeting minutes and updates available on this wiki
    • project wiki
    • Weekly HRP Test planning meetings